Town Hall Renovation

The project proposes to redevelop and enhance the existing Town Hall facility to meet current and projected staffing needs. Goals and priorities include improvements to office space, fire suppression system, HVAC, addition of a formal Town Council Chambers and outdoor gathering space for Town events and public use. Additional improvements include expanded parking, lighting, signage, on-site stormwater, and improved technology to enhance the citizen experience at Town Hall.

This project supports the Town of Bluffton's Strategic Plan Goal of "Upgraded Town Infrastructure and Facilities".

5/29/19

  • Construction completed. Ribbon cutting May 29, 2019 4:30 to 6:00 p.m.

9/7/18

  • Ongoing construction includes interior drywall work, exterior metal roofing and siding. Interior and exterior painting. The estimated completion date is late fall 2018.

5/31/18

  • Construction has begun with an anticipated complete schedule of late 2018.
Tharpe Engineering Group - Structural Engineers
Ward Edwards Engineering - Civil Engineers
CDDC, LLC - Electrical Engineers

JE Dunn Construction
Project Manager: Brian Osborne | 843-706-7817